Garage: Front Wall, Roof Trusses and Decking

With the concrete walls set for the garage, it was time to build the front wall and get the roof trusses in place. . We were dreading the placement of what we simply dubbed, the “big truss”. Big truss is a 300 pound triple truss coming in at 26 feet long. The smaller trusses are singles at 26 feet long, and only weight 95 pounds.

It was key to ensure that the front wall was built properly – it supports the trusses. If the front wall height is incorrect, the roof will not slope properly leading to water drainage issues. Dave used his laser level to sight the wall heights and then ran plumb lines to ensure that everything as built to the appropriate height.

Dave and excavator Dave used his mini backhoe to move big truss into the garage. Big truss was so long, it could not be orientated properly in the build site. Dave and excavator Dave had to move the truss to the shared driveway, orientate it properly, and move it back to the build site (Jess was fortunately not home for this escapade). The escapade Jess got to witness was the lifting of big truss into place with the mini excavator. We are most definitely not a OSHA job site.

After big truss was secure, we used a materials lift (rented) to position the remaining 15 trusses. The materials lift was a back and lifesaver. The trusses were lifted and positioned 16 inches on center on the top plate of the front wall and rear concrete wall. Dave had pre-marked the top plate so the trusses could be quickly placed. Once the truss was in position, a nail gun was used to toe-nail the truss in place. The truss was then secured to a 2 x 4 running horizontally across the top to ensure that it remained 16 inches on center and perpendicular to the top plate. The tricky part to this step was the last two trusses – both had to be lifted to the top plates and secured to big truss. The reason for this was if the penultimate truss was placed, it would have prevented us from using the materials lift to get the last truss set.

Once all the trusses were in place, the materials lift was used to get the decking sheets (Advantech) onto the roof. The first two sheets took the longest because they had to be secured in order to create a platform to place materials and work from. Construction adhesive and screws were used to secure the Advantech sheets to the trusses. Since the sheets are 4’x8′, it was key to have all the trusses 16″ on center to ensure that all the seams were located on a truss. Once the roof decking was on, the entire system was very sturdy.

Upon completion of the roof decking, Dave went on to build a parapet to hold the green roof material and the roof for the window well. To build the parapet wall, roof’s slope was taken into account. The wall is 4 inches high over the garage doors, increasing to 10 inches high to the rear of the garage.

Garage: Footers, Forms, and Floors

One of the hardest points of a construction project is right around the end of excavation. You’ve written checks for architect and engineering fees, variance fees, permit fees, and paid deposits. You are already over projected budgets and time lines, the bank account is depleted, and the credit cards are carrying much higher balances. And all you have to show is one flipping giant hole in the ground.

And then comes mud (concrete), glorious, glorious mud. It’s amazing how just getting footers in can offer a bit of hope. And then the wall forms. And before you know it, there are walls.

Footers pushed us a little further behind schedule. It has been a cool, wet spring in the mountains and that means concrete takes a wee bit longer to set up. Throw in the fact that everyone has been waiting for the good weather, the concrete plants are running at capacity and are struggling to keep up with demand.

After getting the front wall framed and the roof decking installed, it was time to lay radiant flooring (3/4 inch PEX tubing on top of 2 inch foam board on top of 4 inches of crushed stone). Through meticulous planning, the radiant tubes are direct below unused air intakes in the existing foundation wall – no need to drill new holes. (It was really dumb luck, but we’ll take it.) After the tubing passed a pressure test, we were good to go for our pad pour.

With the concrete plants still running 24/7 to barely keep up with demand, we weren’t certain if we were going to be able to pour on Friday. This was key to allow us to do interior framing on Sunday. The framing needs to be done so we can keep on track with electrical rough in and not miss the inspection window. (Missing the inspection window just means more delays.) We found out on Thursday that mud was coming Friday at noon. The small things that help keep us on track.

Some fun info about concrete – it can be mixed at different consistencies. Thicker consistency is used for walls and footers (generally) and sets up quickly. The quick set up time results in a heat quickly and helps prevent the concrete from freezing before it sets in cold temperatures. Thinner consistency is used for floors (need to be floated) and sets up slowly. The heat is released more slowly. Why does this matter? Apparently on a hot summer day you need a mix that is thinner than normal. Otherwise the concrete sets too fast before it can be properly floated. We hired a great team of concrete guys, but they were working hard to make sure things were right before the concrete set.